Demo Mode — All data is simulated. No real funds, accounts, or deals.
Current Draw
Draw #3 · Structural Steel Erection · $2,180,000
All 10 release conditions verified — awaiting funder authorization.
Deal Progress — Harbor Logistics Center
Contract Executed
SOV Approved
Draw Linked
Evidence Reviewed
Authorize Release
Harbor Logistics Center
ACTIVEMarcus Webb · Sarah Chen · Started 180 days ago
Total
$9,100,000
Funded
$9,100,000
Released
$2,160,000
Progress
24%
Evidence — Draw #3 · Structural Steel Erection
Inspection Report — Steel Erection Complete
Uploaded 5 days ago
Conditional Lien Waiver — Webb Construction
Uploaded 5 days ago
Draw Request #3 — $2,180,000
Uploaded 4 days ago
Site Photo — Steel Frame Erection Progress
Uploaded 4 days ago
Your Progress — Harbor Logistics Center
Next: Request AI review for Building Envelope & Roofing — upload supporting documents to proceed.
Milestones
Site Preparation & Grading
$320,000· SOV linked
Released 14 days ago
Supporting Documents
- Inspection Report — Grading Complete
- Lien Waiver — Webb Construction
- Draw Request #1 — $320,000
Concrete Sub-grade & Foundations
$1,840,000· SOV linked
Released 7 days ago
Supporting Documents
- Inspection Report — Foundations
- Lien Waiver — Webb Construction
- Draw Request #2 — $1,840,000
Structural Steel Erection
$2,180,000· SOV linked
Supporting Documents
- Inspection Report — Steel Erection
- Lien Waiver — Webb Construction
- Draw Request #3 — $2,180,000
Perplexity Computer Draw Control Brief
91/100 · low riskDraw #3 for Structural Steel Erection has been independently reviewed. Steel erection is 100% complete per inspection. All supporting documents are in order and all 10 release-gate conditions are satisfied.
✓ Inspection report confirms structural steel erection complete
✓ Conditional lien waiver on file — Webb Construction
✓ No open change orders on this milestone
✓ Sequential prerequisites satisfied — milestones 1 & 2 released
✓ Signed contract on file — Harbor_Logistics_Agreement.pdf
✓ SOV line item linked — $2,180,000 allocated
All 10 release conditions verified. Funder authorization required to proceed.
Building Envelope & Roofing
$2,640,000
MEP Systems & Commissioning
$2,120,000· SOV linked
Schedule of Values
| Line Item | Contract Value | Drawn | Remaining | Status |
|---|---|---|---|---|
| Site Preparation & Grading | $320,000 | $320,000 | $0 | complete |
| Concrete Sub-grade & Foundations | $1,840,000 | $1,840,000 | $0 | complete |
| Structural Steel Erection | $2,180,000 | $0 | $2,180,000 | approved |
| Building Envelope & Roofing | $2,640,000 | $0 | $2,640,000 | pending |
| MEP Systems & Commissioning | $2,120,000 | $0 | $2,120,000 | pending |
| Total | $9,100,000 | $2,160,000 | $6,940,000 |
One or more SOV line items are not linked to a milestone. Link them in the Milestones panel to enable draw-control tracking.
Documents
Deal Agreement — Harbor_Logistics_Agreement.pdf
Signed October 25, 2025
Insurance Certificate — Insurance_Cert_WebbConstruction.pdf
October 25, 2025
Project Schedule — Harbor_Master_Schedule_v3.pdf
October 30, 2025
Activity
Deal created — $9,100,000 total contract value
October 25, 2025
Harbor_Logistics_Agreement.pdf uploaded
October 25, 2025
DocuSign envelope sent for signatures
October 25, 2025
Funder signature completed in DocuSign
October 25, 2025
Contract fully executed — both parties signed
October 25, 2025
Schedule of Values submitted — 5 line items, $9,100,000
October 28, 2025
SOV approved — all 5 line items verified
October 29, 2025
Site Preparation & Grading released — $320,000
14 days ago
Concrete Sub-grade & Foundations released — $1,840,000
7 days ago
Draw #3 evidence uploaded — inspection report, lien waiver, draw request
5 days ago
Draw #3 submitted for review — $2,180,000
4 days ago
AI Draw Review completed — score 91/100, risk: low
3 days ago
Draw Control Brief generated — all 10 release conditions verified
3 days ago
Structural Steel Erection approved — awaiting funder authorization
2 days ago
Release gate verified — 10/10 conditions passed — funder authorization required
2 days ago
Vektrum authorizes release — it does not hold funds or act as escrow. Payment execution is handled by your selected rail: Stripe Connect or your institutional partner process. Funds remain in custody of your payment provider until release is authorized and the execution rail confirms.