Demo Mode — All data is simulated. No real funds, accounts, or deals.
Westside Medical Office Campus
ACTIVEDiane Reyes · Sarah Chen · Started 30 days ago
Total
$4,750,000
Funded
$4,750,000
Released
$950,000
Progress
20%
Milestones
Site Work & Utilities
$475,000
Released 15 days ago
Documents
- Inspection Report — Site Work
- Lien Waiver — Reyes Development
- Draw Request #1 — $475,000
Structural Frame & Enclosure
$1,425,000
Work in progress — draw not yet submitted
Interior Build-Out & MEP
$1,900,000
FF&E, Technology & CO
$950,000
Documents
Deal Agreement — Westside_Medical_Agreement.pdf
Signed March 23, 2026
Insurance Certificate — Insurance_Cert_ReyesDev.pdf
March 23, 2026
Project Schedule — Westside_Schedule_v1.pdf
March 26, 2026
Activity
Deal created — Sarah Chen & Diane Reyes
March 23, 2026
Insurance certificate uploaded
March 23, 2026
Site Work & Utilities milestone released — $475,000
15 days ago
Structural Frame & Enclosure work started
10 days ago
Progress inspection scheduled for Structural Frame
5 days ago