Total Capital Committed

$16,250,000

Total Released to Date

$3,590,000

Held Pending Release

$12,660,000

Allocation by Project

56%
29.2%
Riverside Mixed-Use$2,400,000 (14.8%)
Harbor Logistics$9,100,000 (56%)
Westside Medical$4,750,000 (29.2%)

Release Velocity by Project

Riverside Mixed-Use

active
Released $480K of $2.4M total20%

Released: $480K | Pending: $1.9M

Harbor Logistics

active
Released $2.2M of $9.1M total24%

Released: $2.2M | Pending: $6.9M

Westside Medical

active
Released $950K of $4.8M total20%

Released: $950K | Pending: $3.8M

Milestone Status Distribution

4

Released

2

Approved (pending release)

4

In Review / In Progress

3

Not Started

Recent Releases

DateProjectMilestoneAmount
February 21, 2026Riverside Mixed-UseFoundation & Site Prep$480,000
14 days agoHarbor LogisticsSite Preparation & Grading$320,000
7 days agoHarbor LogisticsConcrete Sub-grade & Foundations$1,840,000
15 days agoWestside MedicalSite Work & Utilities$475,000

Portfolio Health

ProjectRisk LevelAI Score AvgStatus
Riverside Mixed-Use DevelopmentLow89/100On Schedule
Harbor Logistics CenterMedium91/100Dispute Active
Westside Medical Office CampusLow74/100On Schedule
Overall portfolio health: Good — 2 of 3 projects on schedule · 1 dispute in resolution